|
Projects
Emerson Hospital Concord, MA Approximate Contract Amount: $1.7M
Sea & Shore was selected to design and construct temporary
excavation support and underpinning as part of the $45M expansion
of this hospital. Temporary excavation heights of greater than
30ft were retained using soldier pile and timber lagging with
multiple levels of grouted tiebacks. Underpinning of the existing
three-story Birthing Center to allow excavation depths of 20ft for
new foundation construction was accomplished with a complex jet
grout and soil nail system to support both vertical building
loads and lateral earth pressures. Sea & Shore also constructed
multiple vertical tie-down anchors as part of the seismic design of
the new building. Sea & Shore performed all site work operations
including excavation of approximately 20,000 tons of soil, dewatering
of silty, subgrade soils, deep utility and drainage connections, and
general paving and site improvement.
|
|
|
|
Slack's Reservoir Damn Reconstruction Smithfield, RI Approximate Contract Amount: $450,000
Sea & Shore recently completed reconstruction of one of
Rhode Island's high risk dams in Smithfield. This project
included the installation of approximately 260lf of 45ft
long sheet piling with interlock sealant; designing and
construction of a cast-in-place concrete valve pit and water
control structure including deep reservoir drain; slip lining
of 24:" HDPE pipe through an existing granite block culvert;
concrete construction to extend and existing high water
spillway out to the sheet piling wall; and sitework construction
to reshape the entire dam including flattening the dam
backslope and relocating the crest of the dam closer to the new
sheet pile cut off wall.
|
|
|
Lowe's Home Center Dedham, MA Approximate Contract Amount: $1.9M
Sea & Shore installed approximately 1,400 50 ton,
concrete-filled, pipe piles to support the new store
in Dedham, MA. Two pile diving rigs were used over this
two month long project. Simultaneously, Sea & Shore constructed
over 500lf of cantilevered retaining wall as a permanent site
feature around the store. Portions of this retaining wall
were constructed by installing 50ft long 36in diameter pipes
utilizing a state of the art, vibration free static drill/drive
technique developed in Japan. This installation method greatly
reduced construction duration and disturbance to abutters in an
adjacent state highway. This method also substantially reduced
the required construction equipment on site that allowed two pile
driving rigs and the wall construction to occur simultaneously.
Sea & Shore also performed site work to excavate and backfill
for pile caps./grade beams and obstruction removal within the
footprint of the building.
|
Omega Pond Force Main Crossing East Providence, RI
Approximate Contract Amount: $600,000
Sea & Shore was contracted to provide marine construction
services to install approximately 1,000lf of 20in diameter ductile iron
sewer force main through the Omega Pond in East Providence, Rhode Island.
Sea & Shore mobilized a sectional barge, crane, dive crew and supporting
equipment to install the underwater line. The pipe was set on a new,
helical pile cradle system submerged approximately 5 to 8ft below the
water surface. Sea & Shore's dive crew and top side support installed
the pipe line on the cradle system; installed uplift brackets, anchor
hardware, corrosion protection devices; and excavated mud along the pipe
line alignment using airlift and jet pumps. Sea & Shore also constructed
two sheet pile cofferdams ate the ends of the pond to transition the
pipeline from land to water.
|
|
|
|
Temporary Excavation Support Williams College Approximate Contract Amount: $120,000
Sea & Shore designed, constructed and removed a temporary excavation
support systems as part of site development for the new Campus Center
at Williams College. This work included construction of a braced, soldier
pile and lagging wall to retain excavation depths of 15ft immediately
along one of the town's main roads. To complicate the project, bedrock
existed at an approximate depth of 12 to 15ft below grade, which reduced
the option for pile installation. Overhead wires and sensitive utilities
also existed within a few feet behind the wall, therefore, Sea & Shore
installed the piling into holes predrilled through the dense glacial till
and into bedrock. To reduce the height of pilings to avoid the overhead
wires and to control lateral deflections of the wall, we installed
a single level bracing that was removed following wall construction.
|
|
|
JFK Presidential Library Columbia Point, MA Approximate Contract Amount: $1.4M
Sea & Shore was selected by the National Archives and Records
Administration to reconstruct approximately 1,000lf of failing sea
wall and walkway around the John F. Kennedy Presidential Library in
Boston, MA. As part of this project, we removed and reset 2 to 4 ton
armor stones in stone bedding, reconstructed a concrete header and
bollard system, replaced site drainage and lighting along the sea wall,
and repaved over 35,000sf of walkway and plaza.
|
Blackington Commons Development North Attleboro, MA
Approximate Contract Amount: $250,000
Sea & Shore was selected to install approximately 400 timber
piles to support four new buildings at this residential
development. The pilings were installed in a two-phased
construction sequence.
|
Palmers Cove Yacht Club Salem, MA
Approximate Contract Amount: $160,000
Sea & Shore recently completed construction of a new vinyl sheet
pile bulkhead and piling for a new fixed pier/deck at this marina
in Salem, MA. Sea & Shore was responsible for the final design of
the bulkhead, which included 10 permanent tiebacks, a galvanized
waler and bulkhead cap, and installation of sheeting and new greenhart
pilings.
|
Creative Construction Solutions Underground & Underwater
|
|